Rollercoaster

November 17, 2014 Leave a comment

Wanna go on a wildly fun rollercoaster ride? Then watch Erik Meijer’s “One Hacker Way” rant. Right out of the gate, I guesstimate that he alienated at least half of his audience with his opening “if you haven’t checked in code in the last week, what are you doing at a developer’s conference?” question.

I didn’t agree with all of what Erik said (I doubt anyone did), but I give him full credit for sticking his neck out and attacking as many sacred cows as he could: Agile, Scrum, 2 day certification, TDD “waste“, non-hackers, planning poker, the myth of self-organizing teams, etc. Mmmm, sacred cows make the best tasting hamburgers.

Uncle Bob Martin, the self-smug pope who arrogantly proclaimed “If you don’t do TDD, you’re unprofessional“, tried to make light of Erik’s creative rant with this lame blog post: “One Hacker Way!“. Nice try Bob, but we know you’re seething inside because many of your sacredly held beliefs were put on the stand. You seem to enjoy hacking the sacred cows of the reviled “traditional” way of developing software, but it’s a different story when your own cutlets are at steak.

Mr. Meijer pointed out what I, and no doubt many others, have thought for years: agile, particularly Scrum, is a subtle, insidious form of control. At least with explicit, transparent control, one knows the situation and where one stands. With Scrum, the koolaid-guzzling flock is duped into believing they’re in control; all the while being micro-managed with daily standups, burndown charts, velocity tracking, and cutesy terminology. No wonder it’s amassed huge fame and success – managers love Scrum because it makes their job easier and anesthetizes the coders.

My fave laugh-out-loud moment in Erik’s talk was when he presented Jeff Sutherland as the perceived messiah of software development:

messiah

I’ve found that the best books and talks are those in which I find some of the ideas enlightening and some revolting. Erik Meijer’s talk is certainly one of those brain-busting gems.

The test of a first-rate intelligence is the ability to hold two opposing ideas in mind at the same time and still retain the ability to function. – F. Scott Fitzgerald

The Only Approval That Matters

August 25, 2014 Leave a comment

At its core, process agility is all about continuous learning, fast feedback loops, and fluid changeability. Unlike pre-agile methods (and even some currently purported agile methods), which assume that people are forward-marching automatons who “better not make mistakes” and must defend the fort against all external forces of change, process agility accommodates the mental limitations and fallibility of REAL human beings.

Having said that, how agile do you think a process which includes a sign-off list like this is:

Blank Approval

Imagine that whatever has been “approved” by a ceremonial sheet like this is post-facto found to be laced with errors, inconsistencies, and ambiguities due to natural human fallibility. How likely do you think that finders-of-mistakes will publicly point them out, demand a production line stoppage to fix the turds, and suggest that the director-manager-lead approval gauntlet be traversed again? Conversely, how likely do you think that finders-of-mistakes will say “f*ck-it!“, keep their mouths shut, and keep goose-stepping forward with the herd.

fckit

Fear not, dear reader. BD00 has a simple and clean solution to the director-manager-lead approval gauntlet problem. Collapse the list of approvers down to one – the only one that matters:

BD00 Approval

Please submit your plans for BD00 approval in the comments section. As his executive assistant, I can assure you that his stamp/no-stamp decision will be made pronto. However, don’t call us. We’ll call you.

Stuck And Bother

June 5, 2014 2 comments

I’m currently working on a project with a real, hard deadline. My team has to demonstrate a working, multi-million dollar radar in the near future to a potential deep-pocketed customer. As you can see below, the tower is up and the antenna is majestically perched on its pedestal. However, it ain’t spinning yet. Nor is it radiating energy, detecting signal returns, or extracting/estimating target information (range, speed, angle, size) buried in a mess of clutter and noise. But of course, we’re integrating the hardware and software and progressing toward the goal.

radar pics

Lest you think otherwise, I’m no Ed Snowden and those pics aren’t classified. If you’re a radar nerd, you can even get this particular radar emblazoned on a god-awful t-shirt (like I did) from zazzle.com:

Tshirt-49

OK, enough of this bulldozarian levity. Let’s get serious again – oooh!

As a hard deadline approaches on a project, a perplexing question always comes to my mind:

How much time should I spend helping others who get “stuck“, versus getting the code I am responsible for writing done in time for the demo? And conversely, when I get stuck, how often should I “bother” someone who’s trying to get her own work done on time?

Of course, if you’re doing “agile“, situations like this never happen. In fact, I haven’t ever seen or heard a single agile big-wig address this thorny social issue. But reality being what it is, situations like this do indeed happen. I speculate that they happen more often than not – regardless of which methodology, practices, or tools you’re using. In fact, “agile” has the potential to amplify the dilemma by triggering the issue to surface on a per sprint basis.

Save for the psychopaths among us, we all want to be altruistic simply because it’s the culturally right thing to do. But each one of us, although we’re sometimes loathe to admit it, has been endowed by mother nature with “the selfish gene“. We want to serve ourselves and our families first. In addition, the situation is exacerbated by the fact that the vast majority of organizations unthinkingly have dumb-ass recognition and reward systems in place that celebrate individual performance over team performance – all the while assuming that the latter is a natural consequence of the former. Life can be a be-otch, no?

 

Categories: technical Tags: , ,

A Skeptical “No”

May 5, 2014 7 comments

Just about every agile video, book, and article I’ve ever consumed assumes some variant of the underlying team model shown below. The product these types of teams build is comprised of custom software running on off-the-shelf server hardware. Even though it’s not shown, they also assume a client-server structure, request-response protocol, database-centric system.

SW only

The team model for the types of systems I work on is given below. They are distributed real-time event systems comprised of embedded, heterogeneous, peer processors glued together via a pub-sub protocol. By necessity, specialized, multi-disciplinary teams are required to develop this category of systems. Also, by necessity, the content of the sprint backlog is more complex and intricately subtler than the typical agile IT product backlog of “features” and “user stories“.

SW and HW

When I watch/read/listen to smug agile process experts and coaches expound the virtues of their favorite methodology using narrow, anecdotal, personal stories from the database-centric IT world, I continuously ask myself “can this apply to the type of products I help build?“. Often, the answer is a skeptical “no“. Not always, but often.

The Last Retrospective

April 20, 2014 Leave a comment

In an ongoing agile endeavor, the practice for eliciting and applying freshly learned knowledge going forward is the periodic “retrospective” (aka periodic post-mortem to the “traditional” old fogeys). Theoretically, retrospectives are temporary way points where individuals: stop, step back, cerebrally inspect what they’ve accomplished and how they’ve accomplished it, share their learning experiences, suggest new process/product improvements, and evaluate previously implemented improvements.

As the figure below depicts, the fraction of newly acquired knowledge applied going forward is a function of group culture. In macho, command and control hierarchies like culture B, the application of lessons learned is suppressed relative to more flexible cultures like A due to the hierarchical importance of opinions.

Gained Vs Applied

Regardless of culture type, during schedule-challenged projects with a fixed, do-or-don’t-get-paid deadline (yes, those projects do indeed still exist), this may happen:

Last Retrospective

When the elites upstairs magically determine that a panic point has appeared (sometimes seemingly out of nowhere): retrospectives get jettisoned, the daily standup morphs into the daily inquisition, corner-cutting “practices” become best practices, and the application of newly acquired knowledge stops cold. Humans being humans, learning still naturally occurs and new knowledge is accrued. However, it is not likely the type of knowledge that will help on future projects.

Importance Of Opinion

April 18, 2014 6 comments

Regardless of whether a project is managed as an agile or traditional endeavor, it is well known that the execution team learns and acquires new knowledge as the project lurches forward. It is also well known that individual team members learn and formulate opinions that may be at odds with each other.

In spite of the “we’re all (equal)” scrum mantra, some individual opinions will always be “more important” than others in a hierarchy… because that’s what a social hierarchy does (POSIWID). The taller the hierarchy, the larger the gap of importance between opinions. And the larger the gap of importance between opinions, the lesser the chance that a diverse subset of newly acquired knowledge will be applied to future project activities.

The figure below shows two concepts of “Importance Of Opinion“. On the left, we have the Scrum ideal – we’re all one and all opinions carry the same weight. On the right, we have the reality. The opinions within the pyramid of elite titles strongly influence/skew/suppress the PO’s opinions, the PO does the same to the SM, and the SM does the same to the group of DEVs. Even within the so-called flat structure of the DEVs, all opinions are not created equal.

Theory And Reality

Categories: management Tags: , , ,

Don’t Be Fooled

April 11, 2014 2 comments

Check out the hypothetical agile burndown and EVM (Earned Value Management) charts below. Like in the “real” world, the example project (or sprint, if you prefer) ended up being underestimated. The shortfall is indicated by the dotted line on the right.

uninverted

When we literally flip the agile burndown chart in the vertical dimension, we get this:

inverted

The moral of the story is: “Don’t be fooled by the agilista herd; an agile burndown chart is nothing but an inverted version of the despised EVM chart.

Formal Waterfall Events

March 31, 2014 2 comments

The customers of all the big government-financed sensor system programs I’ve ever worked on have required the aforementioned, waterfall, dog-and-pony shows as part of their well-entrenched acquisition process. Even prior to commencing a waterfall death march, as part of the pre-win bidding process, customers also (still) require contractors to provide detailed schedule and cost commitments in their proposal submissions – right down to the CSCI level of granularity.

If you think it’s tough to get your internal executive customers to wholeheartedly embrace an “agile adoption” or “no estimates” initiative, try to wrap your mind around the cosmic difficulty of doing the same to a large, fragmented, distributed authority, external acquisition machine whose cogs are fine-tuned to: cover their ass, defend their turf, and doggedly fight to keep the extant process that justifies their worth in place. Good luck with that.

Go Agile

Dueling Quagmires

March 21, 2014 2 comments

To BD00, the agile movement, even though it is a refreshing backlash against the “Process Models And Standards Quagmire” (PMASQ) perpetrated by a well-meaning but clueless mix of government and academic borgs who don’t have to create and build anything, has spawned its own quagmire of “Agile Process Frameworks And Practices Quagmire” (APFAPQ). Like the PMASQ community has ignited a cottage industry of expensive consultants, certifiers, assessors, trainers, and auditors, the APFAPQ movement has jump-started an equivalent community of expensive consultants, coaches, trainers, certifiers.

Dueling Quags

Not That Different, No?

March 7, 2014 4 comments

Check out this slide I plucked from a pitch that will remain unnamed:

Agile Vs WF

Notice the note under the waterfall diagram. Now, let’s look at the original, “unadapted” version and accompanying quote from Winston W. Royce’s classic 1970 paper:

Seq WF

Notice that Mr. Royce clearly noted in his paper that the sequential, never-look-back, waterfall process is a stone cold loser. Next, let’s look at another diagram from Mr. Royce’s paper; one that no fragilista ever mentions or shows:

Iterative WF

OMG! An iterative waterfall with feedback loops? WTF!

Finally, let’s look at BD00’s syntegrated version of the agile, lower half of our consultant’s diagram and the iterative waterfall diagram from Mr. Royce’s paper:

Agile WF

Comparing the agile and “chunked“, iterative, waterfall models shows that, taken in the right context, they’re not that different…. no?