Don’t Be Fooled

April 11, 2014 2 comments

Check out the hypothetical agile burndown and EVM (Earned Value Management) charts below. Like in the “real” world, the example project (or sprint, if you prefer) ended up being underestimated. The shortfall is indicated by the dotted line on the right.

uninverted

When we literally flip the agile burndown chart in the vertical dimension, we get this:

inverted

The moral of the story is: “Don’t be fooled by the agilista herd; an agile burndown chart is nothing but an inverted version of the despised EVM chart.“

Burn Baby Burn

The “time-boxed sprint” is one of the star features of the Scrum product development process framework. During each sprint planning meeting, the team estimates how much work from the product backlog can be accomplished within a fixed amount of time, say, 2 or 4 weeks. The team then proceeds to do the work and subsequently demonstrate the results it has achieved at the end of the sprint.

As a fine means of monitoring/controlling the work done while a sprint is in progress, some teams use an incarnation of a Burn Down Chart (BDC). The BDC records the backlog items on the ordinate axis, time on the abscissa axis, and progress within the chart area.

BDC Template

The figure below shows the state of a BDC just prior to commencing a sprint. A set of product backlog items have been somehow allocated to the sprint and the “time to complete” each work item has been estimated (Est. E1, E2….).

Empty BDC

At the end of the sprint, all of the tasks should have magically burned down to zero and the BDC should look like this:

Perfect BDCSo, other than the shortened time frame, what’s the difference between an “agile” BDC and the hated, waterfall-esque, Gannt chart? Also, how is managing by burn down progress any different than the hated, traditional, Earned Value Management (EVM) system?

I love deadlines. I like the whooshing sound they make as they fly by – Douglas Adams

In practice, which of the outcomes below would you expect to see most, if not all, of the time? Why?

Burn Baby Burn

We need to estimate how many people we need, how much time, and how much money. Then we’ll know when we’re running late and we can, um, do something.