The Drooping Progress Syndrome
When a new product development project kicks off, nobody knows squat and there’s a lot of fumbling going on before real progress starts to accrue. As the hardware and software environment is stitched into place and initial requirements/designs get fleshed out, productivity slowly but surely rises. At some point, productivity (“velocity” in agile-ese) hits a maximum and then flattens into a zero slope, team-specific, cadence for the duration. Thus, one could be led to believe that a generic team productivity/progress curve would look something like this:
In “The Year Without Pants“, Scott Berkun destroys this illusion by articulating an astute, experiential, observation:
This means that at the end of any project, you’re left with a pile of things no one wants to do and are the hardest to do (or, worse, no one is quite sure how to do them). It should never be a surprise that progress seems to slow as the finish line approaches, even if everyone is working just as hard as they were before. – Scott Berkun
Scott may have forgotten one class of thing that BD00 has experienced over his long and un-illustrious career – things that need to get done but aren’t even in the work backlog when deployment time rolls in. You know, those tasks that suddenly “pop up” out of nowhere (BD00 inappropriately calls them “WTF!” tasks).
Nevertheless, a more realistic productivity curve most likely looks like this:
If you’re continuously flummoxed by delayed deployments, then you may have just discovered why.
Related articles
- The Year Without Pants: An interview with author Scott Berkun (oldienewbies.wordpress.com)
- Scott Berkun Shares Advice for Writers Working Remotely (mediabistro.com)
- A Book in 5 Minutes: “The Year without Pants: WordPress.com and the Future of Work” (tech.co)